Pollmann
Vitis (NÖ / A)
Automotive
www.pollmann.at
- New production site / expansion stage 1
- Energy and logistics concept
- MSR-implementation planning/realization
- Handling environmental funding
- Project support logistics a. energy
- Partner: PENEDER
- Status: MSR acceptance 09/2019
- Suppor
NGR
Feldkirchen a. d. Donau (OÖ / A)<br/>Recycling machines<br/> https://www.ngr-world.com/de/
- Expansion production site
- Energy and logistics concept
- Funding processing KPC a. AWS
- MSR-implementation planning/realization
- Project support logistics a. energy
- Partner: PENEDER
- Status: MSR acceptance 03/2022
- Support 1st operating year
Langmatz
Oberau (Bay / D)
Cable ducts
www.langmatz.de
- Expansion production site
- Energy and logistics concept
- MSR-implementation planning/realization
- Project support logistics a. energy
- Partner: PENEDER
- Status: MSR acceptance 12.2020
- Support 1st operating year
Agilox
Lambach (OÖ / A)
Automated guided vehicle systems
www.agilox.at
- New headquarters
- MSR-implementation planning/realization
- Partner: PENEDER
- Status: MSR acceptance planned 01/2021
- Support 1st operating year
Peneder Base
Atzbach( OÖ / A)<br/>Business construction<br/> https://www.peneder.com/de-at/bau-architektur
- Exchange and modernization of the complete building control engineering
- MSR-implementation planning/realization
- Status: MSR acceptance 11/2022
STIWA Group
Attnang-Puchheim & Gampern (OÖ / A)
- MSR-implementation planning/realization
- Status: Constant building support
Gaplast
Peiting (Bay / D)
Packaging solutions
www.gaplast.de
- Expansion production site
- Energy and logistics concept
- MSR-implementation planning/realization
- Project support logistics a. energy
- Additional orders automatical locks/Agilox clean room
- Partner: PENEDER
- Status: MSR acceptance planned 12/2021
- E-OPF-FM & Support since 2012
Asma
Weitra (NÖ / A)
Plastic molding
https://asma.polyurethane.at/
- Expansion production site
- Energy and logistics concept
- MSR-implementation planning/realization
- Project support logistics a. energy
- Partner: PENEDER
- Status: MSR acceptance expansion 12.2020
- E-OPT-FM since 2013
Peneder
Fraham (OÖ / A)<br/>Fire protection elements<br/> https://www.peneder.com/de-at/brandschutz
- Energy and process optimization
- Conversion powder coating to wood chips
- CO2-neutral location
- Funding processing KPC a. AWS
- MSR-implementation planning/realization
- Partner: PENEDER
- Status: MSR acceptance planned 12/2021
- E-OPT-FM and Support since 2022
Dr. Grandel
Augsburg (Bay / D)
Cosmetics
www.grandel.de
- Energy and process optimization
- Conversion heating to long-distance heating
- Conversion electricity procurement to green electricity
- MSR-implementation planning/realization
- Partner: PENEDER
- Status: MSR acceptance 07.2018
- E-OPT-FM since 2018
- Support since 2019
Oberbank
Linz (OÖ / A)
Bank services
www.oberbank.at
- Energy Audit for central offices since 2011
- Energy Audit according to EEffG 2014
- Energy Audit according to EEffG 2018
- Status: Development CO2-strategy